Thursday, April 1, 2010

.: Renovation Work : Part 9 :.

Alhamdulillah, after 3 weeks of renovation works, finally everything completed..Thanks to all the contractors for the superb + great job!!

Yesterday we went to the house again to do final checking with Subra for the wiring works..After satisfy with their works, I paid him RM3700 for the balance..So total for the wiring cost is RM5200, that include wiring for the whole house + installation for fans + lights + door bell..

Then me and family spent few more hours to wash + clean the house..Anyway below is the latest summary on the renovation works :

1. Renovation Work on 10th and 11th Day

-Wiring work completed. Total cost is RM5200
-Wrought iron installation completed. Need to do final check on the finishing before we pay for the balance :)

As for now, everything seems to be ready to move in..The only thing that need to be done + pending jobs are :

1) Take measurement for the curtain and we will assign Teewah for the sewing job
2) Installation of roller-blind for dry kitchen
3) Installation of kitchen cabinet by Patric - Appointment on 10th April 2010
4) Make arrangement with the transportation for the moving

I think that's for now..I'll update more with the latest info on the next post :)..