This morning I had 2 appointments with the wire-man + check all the defects..1st appointment @ 10am with Subra..He is my friend contractor, and after counting how many points + downlight + fan + aircond that we need, he will quoting us the price by tomorrow..
Then, I met up with Mohamad, contractor recommended by Bahari..Same goes with him, calculating how many things that we needed, then he quoting us RM5100 for it..That's including all the wiring + installation of all the electric stuff..Anyway, I need to wait for Subra quotation, so that I can compare both of the price :)..
After that, I'm alone do the house inspection, to check all the defects that the house have..I already marked it with the tape + writing down on the defects list and send it to developer..They promise to finish + touch up all the defects by 2 weeks at least..
Anyway below is the latest update for the checklist of renovation work :
1. Get MPSJ permission for the renovation work - Status : DONE. Didn't require permit since the renovation work is done inside the house..The permit will be needed if the renovation is done outside the house
2. Get developer permission for the renovation work - Status : Submit the permission letter on Saturday 6th March
3. Measurement for KC has been done by Patric - Status : DONE. Next step, awaiting my confirmation when they can start their work
4. Design for the Grill has been confirmed. Appoint Bahari for it - Cost : RM7116 (Wrought Iron for complete home),RM9116 (Wrought Iron for complete home + Gate) - Status : They can start their work, awaiting for the final output :)
5. Got quotation from KH Construction Metal Works for the Grill - Cost : RM5800, Wrought Iron (hollow) for complete home - Status : Canceled
6. Got quotation from Orbit Networking Marketing for the Auto Gate - Cost : RM2400, Auto Gate, with Cable Armour Conceal - Status : Will Consider
7. Got quotation from Lai for the PS - Cost : RM3867.60 (installation + materials) Status : Confirmed the PS design
8. Got quotation from Haji for the PS - Cost : RM3200 (workmanship) + RM2000 (price estimation for the material) - Status : Canceled
9. Met with Subra wire-man Status : Awaiting for the quotation
10. Call Baha Wire-man for the appointment - Status : Canceled
11. Got quotation from Mohamad for the wiring - Cost : RM5100 - Status : Will consider
12. Submit defect list to developer - Status : Done, awaiting for them to fix the defect